In construction it is not unusual for more than one party to be responsible for a breach of contract. For example, there may be a design fault, a failure to inspect, and poor workmanship, all contributing to a defect in the works. Under common law (the Civil Liability (Contribution) Act 1978) all parties can be jointly and severally liable for the loss or damage that flows from the breach.
This means that the client can pursue the parties either jointly, or individually (severally) for the full amount of the loss. If the client decides to pursue one of the parties for the full amount, then that party may in turn pursue the other parties that contributed to the breach to recover their share of the amount claimed.
In practice, the claimant may decide to pursue the parties jointly, and allow the court to apportion liability between them (NB: This is not a matter of proportionate liability, which does not exist in English law, but is simply the apportionment of the full liability in contribution proceedings). However, 'several' liability can be of benefit to the client, if for example, the contractor becomes insolvent, allowing them to recover all of their losses from the remaining parties.
This can leave consultants and contractors open to very large claims, making them jointly and severally liable with parties that they did not themselves appoint, and whose performance they have little influence over.
The Latham report proposed that joint and several liability should be replaced by 'proportionate liability'. However, this was rejected by the Secretary of State for Trade and Industry Peter Mandelson. His position was endorsed by the British Property Federation (a body that represents the interests of construction clients).
The amount that can be recovered from one party can be limited by a net contribution clause. This restricts liability to the amount for which the party being pursued is responsible. Other amounts must be recovered from the other parties. Net contribution clauses assume that parties responsible for the same loss or damage are all contractually liable to the other party to the contract, and that they have paid the share that they would have been apportioned under common law.
Clients tend to resist net contribution clauses as they transfer the risk of not being able to recover losses onto the client. Whilst this is fair in that the client did appoint all the parties, the client themselves are completely innocent of the breach.
Net contribution clauses have become increasing popular in appointment agreements and collateral warranties. Questions remain however about whether they are always enforceable, for example where one of the parties to whom liability is apportioned is not present in court. However, in 2009, in the Scottish case of Langstane Housing Association v Riverside Construction (Aberdeen) Ltd, the court seemed to accept that this sort of clause was not unusual and that the client could, if they wanted, insure themselves against unrecoverable losses.
[edit] Related articles on Designing Buildings Wiki
- Causes of construction disputes.
- Civil procedure rules.
- Contract claims.
- Contribution and apportionment.
- Defects.
- Design liability.
- Latham report.
- Net contribution clauses.
- Loss and expense.
- Professional indemnity insurance.
- Strict liability.
[edit] External references
- Building: Latham's legacy.
- Joint and Several Liability in the Construction Industry: Is it time for law reform in the UK? (2004).
- Hugh James: Net Contribution Clauses in Construction Contracts - Are they fair and reasonable?
- Civil Liability (Contribution) Act.
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.